Gantry crane manufacturers to explain the design overhaul Taiwan


bridge gantry crane manufacturer maintenance station to explain the design:
①, repair station installation location: at the general layout of the rigid leg.
②, repair station for a group of two. Can be designed as a fixed type. Between two maintenance units have electric hoist through space. Distance: 800 mm.
③, overhaul flat-screen distance away from the beam bottom flange of 1400 mm. This highly convenient for maintenance hoist.
④, overhaul platform length: generally the rigid outrigger width. Objective: easy installation.
⑤, repair station frame with the 8th channel production. With 3 mm thick textured board veneer. Objective: To slip.
⑥, 1050 mm high maintenance stage of the fence. Fence on the baseboards, to prevent tools fall.
⑦, repair station to connect one end of legs reinforced with a triangular plate welding.
⑧, overhead gantry crane   proposals overhaul Taiwan indent the other end of 300-400 mm, with a flat iron two-4X60 with legs welded connection. Purpose: electric hoist trolley slip line (rubber line) interfere with the maintenance station run time.
⑨, overhaul bed design computational load: 2500N / / m ^ 2.